Roxbury Northfield (VT 12A)
ER STP 0187(13)
Project Location: The project extends along VT 12A from
about 3/4 of a mile north of the Granville/Roxbury Town Line
in Roxbury to the Northfield Village Limits for a distance of
9.6 miles.
ROUGH ROAD – VT 12A between Roxbury and Northfield has a
gravel road surface. Drivers are warned to exercise extreme caution
on granular surfaced roadways in a work zone. Punctured
tires and windshield damage could occur if material flies up
from the surface of the road. Maintain a safe distance between
vehicles and obey the speed limit. VT 12A will continue to be
monitored for dust and potholes throughout the week and over
the weekends.
Week of August 7, 2017
There will be several active construction operations within the
project this week. Expect traffic delays on VT 12A this week.
Roxbury:
• Ditching crews will be working between Cram Hill Road and
Sullivan Hill Road.
Northfield:
• Crews will be placing new stone material between Winch Hill
Road and Potato Hill Road. Expect heavy truck traffic.
Travel will be reduced to one lane with alternating one way traffic
around all operations. Flaggers will be present to assist in
maintaining traffic flow.
Traffic – Traffic delays are expected this week.
It is illegal in VT to use any handheld portable electronic devices
while driving. The law carries fines of up to $200 with points
assessed if the violation occurs in a work zone.
Contact Francine Perkins, Project Outreach Coordinator, FRP
Enterprises, LLC with any questions or concerns with regards to
the project at 802-479-6994. Construction updates will be posted
at www.roadworkupdates.com

Return to top

Post new comment

The content of this field is kept private and will not be shown publicly.
By submitting this form, you accept the Mollom privacy policy.




 
Northfield Municipality

The American Legion



Kindergarten

Gifford

Vermont Energy